Agreement 0011116, filed with the Texas Comptroller by Tom Green County, Texas.
Where a deadline above has passed, no public record exists of whether it was met — not in the Comptroller’s filings, nor in the local government’s own disclosures. That is not evidence of non-compliance. Texas requires nobody to record it.
A local abatement waives only that taxing unit’s share of the property tax bill. School districts, counties, cities and hospital districts each sign separately.
| Field | Value & quoted source | Page |
|---|---|---|
| Granting body | Tom Green County, TexasThis Tax Abatement Agreement (the “Agreement”) is made and entered into by and between Tom Green County, Texas (the “County”) | 3 |
| Contracting entity | Cold Creek Solar LLCCold Creek Solar LLC, a Delaware limited liability company | 3 |
| Parent / guarantor | Not stated in the agreement | — |
| Instrument | Tax Abatement AgreementThis Tax Abatement Agreement (the “Agreement”) | 3 |
| Governing chapter | Chapter 312, Tax Code (property tax abatement)and WHEREAS, the Commissioners Court designed and created the Tom Green County Cold Creek Solar Reinvestment Zone Number 1 on February 11, 2025 as authorized by Chapter 312 of the Texas Tax Code to encourage and facilitate such development; | — |
| Capital investment | Not stated in the agreement | — |
| Grant or incentive | Not stated in the agreement | — |
| Jobs committed | Not stated in the agreement | — |
| Wage requirement | Not stated in the agreement | — |
| Square footage | Not stated in the agreement | — |
| Acreage | 1,110.90Total 1,110.90 | 27 |
| Performance deadline | December 31, 2027Owner anticipates that the Project and Improvements will achieve Commercial Operations on or about December 31, 2027. | 6 |
| Expiration | Not stated in the agreement | — |
| Effective date | January 29, 2025January 29, 2025 | 3 |
| Signatory | Not stated in the agreement | — |
| Chain status | Terminal document — no later agreement in the registry names this one as its predecessor | — |
Substation, Transmission Line, Power conversion system (i.e., inverter, transformer, etc.), Foundations, Posts and Racking Equipment, Meteorological Towers and Equipment, Mounting and Tracking Equipment, Solar Modules & Panels, Auxiliary Equipment (i.e., Switchgear, Transformer, switchboard, etc.), SCADA Equipment, Operations and Maintenance Buildings, Roadways, Paving, and Fencing
Open the signed agreement (PDF, Texas Comptroller) →
Agreement 0011116 is filed with the Texas Comptroller. Pull the PDF, go to the page number beside any row, and read the sentence. If a figure here does not match the document, tell me and it is corrected the same day.
Where the contract says nothing, the field is left empty rather than filled with a guess.
For a specific agreement, I read the signed PDF and send back every obligation, deadline and repayment clause, quoted with its page.